GK Engineers is providing full MEP design for Trinity Turbine Technology's expansion in Rosharon, a new 100,000 SF turbine service building alongside a renovation of the existing plant.

LOCATION

Rosharon, Texas

COMPLETED

In Design

SIZE

100,000

CONSTRUCTION COST

$15M

GK Engineers is providing full MEP design for Trinity Turbine Technology’s expansion in Rosharon, a new 100,000 SF turbine service building alongside a renovation of the existing plant. The new pre-engineered building has a crane-served rotor bay, balancing machines that handle 120,000-pound parts, NDE stations, welding, high racking and two-level offices.

GK’s electrical study found the site’s two 2,000 kVA transformers carrying only 1,383 kVA of combined peak load. The design ties the existing switchboards onto one transformer and reuses the freed unit for the new building through a new 4,000A switchboard, avoiding a new utility transformer with a 52-week lead time and taking a year of procurement risk off the schedule.

The new building is about 85 percent conditioned. GK issued 60 percent construction documents in September 2026 and meets weekly with the design-build contractor, owner and architect.